The real cost is rarely the paint
On an occupied commercial building, the coating is a minor line. The expensive items are access, downtime, and doing the same work twice because the sequence was wrong.
We have priced warehouses where the scaffolding and out-of-hours allowance exceeded the material cost several times over. Which means the planning, not the paint, is where a programme is won or lost.
Sequence, and why it saves the most money
- 1Roof and water related work first. Coating internal walls or ceilings below a roof that still leaks is money spent twice, and it is the single most common commercial mistake.
- 2High level and access dependent work next, while the scaffolding or access equipment is already standing. Every separate return visit is a fresh access cost.
- 3Substrate repairs, rust treatment and steelwork after that.
- 4Wall decoration and line marking last, because it is the fastest to complete and the easiest to schedule around trade.
Working around an occupied building
| Constraint | How we work with it |
|---|---|
| Retail trading hours | Night and early morning shifts on customer facing areas, low odour water based systems, full make good before opening. |
| Warehouse operations | Zone by zone with agreed exclusion areas, aisle by aisle sequencing, work planned around stock movement. |
| Offices and tenanted floors | Floor by floor and out of hours, with low odour products and each area handed back usable each morning. |
| Food handling and clinical areas | Product selection to suit, strict containment, wash down and sign off before handover. |
| Schools and institutions | Term breaks and holidays, with a programme committed to in writing well ahead. |
None of that is unusual, but all of it has to be priced honestly. An out of hours programme costs more per square metre than a daytime one, and any quote that ignores the constraint has simply not planned for it.
What the tender document should require
- Measured areas by elevation, zone and level.
- A condition report, including roofs, gutters, parapets and steelwork.
- Preparation specified per substrate, with primer named.
- Coats and litres per zone, so material delivery can be checked.
- Access strategy and who provides it.
- Programme with shift patterns, plus the disruption plan.
- Health and safety file, work at height plan, public liability cover and COIDA letter of good standing.
- Guarantee wording, with what voids it, and a retention held to completion of the punch list.
What we bring to a commercial programme
A survey and written condition report, a scope you can tender on fairly, one fixed price for the whole programme, a shift pattern that protects your trading, and weekly photographic progress. Where a roof or a damp problem will undermine the decoration, that is dealt with first or it is written down as a risk you have accepted knowingly.